Overview
Client: Global logistics real estate investor
Asset locations: Texas, Maryland, New Jersey and Washington
Asset type: Industrial
Summary: The client commissioned GreenGen to conduct feasibility reviews on a portfolio of industrial properties to evaluate data center conversion potential.
Background
GreenGen completed the feasibility review to evaluate the conversion of a portfolio of industrial assets into data centers. With powered land now among the most valuable commodities in commercial real estate, the client sought to identify which properties could capture that value. The review assessed each site across eight categories and delivered a defensible ranking that identified assets with the strongest conversion economics.
Challenge
Data center feasibility depends on factors well outside a typical industrial underwriting process. Power availability, utility tariff structure, grid reliability and building performance regulation all shape the cost to convert and the cost to operate. With assets in four utility territories and regulatory environments, a direct comparison required a common framework. Key considerations identified by the GreenGen team included:
- Existing electrical service far below data center demand at every site
- Wide variation in energy supply rates and demand charges across markets
- Differing grid reliability profiles and regional supply risk
- Lot sizes below the 10-acre threshold that supports expansion and economies of scale
Solution
An Eight-Category Screening Framework
GreenGen developed a standardized screening framework and applied it consistently across the portfolio. Each asset was rated low, medium or high risk in every category, and the results rolled up to an overall opportunity rating. All findings were supported by publicly available data from the EIA, NERC, regional grid operators and published utility rate schedules, giving the client a transparent basis for investment decisions.
Key elements of the review included:
- Capacity: Comparing existing electrical service to the load required for a standard data center, assuming 60 percent of gross area dedicated to servers
- Grid stability: Benchmarking three years of utility outage frequency and duration against the U.S. average, supported by NERC regional reliability assessments
- Communication network: Confirming proximity to major fiber optic distribution infrastructure
- Energy rate: Breaking down each tariff into fixed fees, supply rates and demand charges to project operating cost
- Zoning: Reviewing current zoning designations and local treatment of data center uses
- Regulation: Assessing exposure to building performance standards and emissions thresholds
- Market: Evaluating colocation and hyperscale activity and demand within a 20-mile radius
- Lot size: Measuring acreage against the 10-acre threshold that supports future expansion
Utility Rate Comparison
| Market | Utility | Fixed fee ($/month) | Supply rate ($/kWh) | Demand rate ($/kW) |
|---|---|---|---|---|
| Texas | Oncor | $34.52 | $0.06 to $0.07 | $10.85 to $12.87 |
| Maryland | BGE | $97.00 | $0.0941 to $0.1235 | $5.39 |
| New Jersey | PSEG | $370.81 | $0.07957 | $32.06 + $13.93 (Jun to Sep) |
| Washington | PSE | $218.16 | $0.09549 | $11.47 to $16.90 |
Note: Texas supply rate reflects competitive retail pricing in a deregulated market. 2024 U.S. average industrial supply rate: $0.0815/kWh.
Portfolio Screening Results
| Category | Texas | Maryland | New Jersey | Washington |
|---|---|---|---|---|
| Capacity | High risk | High risk | High risk | High risk |
| Grid stability | Medium risk | Low/Med risk | Low/Med risk | Low risk |
| Communication network | Low risk | Low risk | Low risk | Low risk |
| Energy rate | Low risk | Medium risk | High risk | Medium risk |
| Zoning | Low risk | Low risk | Low/Med risk | Low risk |
| Regulation | Low risk | Medium risk | Low risk | Low risk |
| Market | Low risk | Medium risk | High risk | Low risk |
| Lot size | 6.4 acres, Low/Med risk | 4.6 acres, Medium risk | 8.9 acres, Low risk | 1.6 acres, High risk |
| Overall review | High opportunity | Medium opportunity | Low/Medium opportunity | Low opportunity |
Results
The review gave the client a clear view of where data center conversion creates value and where it does not. Every site would require a new substation, with required service ranging from 87,000 kVA to 390,000 kVA, and every site sat within a mile of major fiber. The differentiators were cost of power, lot size and market depth. GreenGen recommended advancing the Texas asset, the site with the strongest operating economics, to detailed feasibility.
- High-opportunity asset identified: Texas combined the lowest energy cost in the portfolio, a location within an established major metro data center market, and no building performance standard in force.
- Lowest supply rate in the portfolio: A projected supply rate of 6 to 7 cents per kWh in a deregulated market, below the 2024 U.S. industrial average of 8.15 cents. Energy cost is a primary driver of data center operating economics.
- Clear prioritization: Three sites ranked lower with documented rationale, including high demand charges, building performance standard exposure and lot size constraints.
- Repeatable screening methodology: A consistent, data-backed framework that can be applied to additional assets as the client evaluates data center opportunities across its portfolio.
Why it matters
A preliminary screen is a cost-effective way to compare multiple assets before commissioning detailed studies. It identified the site most likely to pencil, with a written record of why the others ranked lower.